Skip to main content
Projects / Mining
Mining Bowen Basin

Bowen Basin Conveyor — PLC-5 to ControlLogix Migration

PLC-5 migration on a 7km overland conveyor system during a 4-day planned shutdown. Full logic audit, off-site simulation, and zero commissioning overrun.

01 Challenge

A 7km overland conveyor running on legacy Allen-Bradley PLC-5 hardware was experiencing increasing fault frequency and parts were no longer available through standard channels. A catastrophic failure mid-season would have cost days of lost production.

02 Solution

Full logic audit and I/O documentation completed over 6 weeks on-site prior to shutdown. ControlLogix replacement program written against a simulation bench with live I/O mapping verified. Hardware pre-built and tested in Mackay workshop. Shutdown used for physical swap, I/O commissioning, and handover only.

03 Outcome

Migration completed within the 4-day shutdown window. Conveyor handed back with full I/O verification, updated drawings, and commissioning records. No faults in the 12 months following cutover.

The situation

Overland conveyors in Bowen Basin coal operations run continuously through the production season. Any unplanned stoppage — whether from a mechanical failure or a control system fault — immediately affects coal movement from pit to train loadout.

The PLC-5 system on this conveyor had been in service for over 20 years. Spare processor cards were sourced from the secondary market at significant cost. The site electrical team had documented three near-miss events in the prior 12 months where a main processor fault had required a manual restart sequence.

The decision to migrate was straightforward. The timing — within the constraints of a planned shutdown window — required careful planning.

The engineering approach

The critical element of this project was front-loading the engineering work. We spent 6 weeks on the site prior to shutdown:

  • Full I/O audit of the existing control panels, verifying wiring against aging drawings and correcting discrepancies
  • Logic capture from the PLC-5 program, translated to commented ControlLogix structured text
  • Signal simulation on a workshop bench with the new hardware, running the translated program against simulated I/O states

By the time the shutdown window opened, the ControlLogix hardware was fully assembled, configured, and tested. The shutdown was used for three things only: physical hardware swap, field I/O verification, and handover walk-through with the site electrical team.

Result

The conveyor was handed back inside the planned window with a complete commissioning record, updated as-built drawings, and a structured fault-finding guide for the maintenance team. The site electrical team can now order spare parts from standard Rockwell distributors.

Technologies used
Rockwell ControlLogix 5580 Studio 5000 Logix Designer RSLinx Enterprise EtherNet/IP FactoryTalk View SE

"We had engineers from three different firms tell us the PLC-5 could not be migrated in a 4-day window. Beetle had it done in three and a half."

Maintenance Superintendent Bowen Basin Coal Operation
Services involved

What we delivered

All services →

Similar project on your site?

Get in touch to discuss what's involved. We work across mining, sugar, manufacturing and utilities in Central Queensland.