Skip to main content
Projects / Sugar Mills

Mackay Sugar PLC Migration — 36h Hand-back

Complete PLC platform migration across three mill drives during a 36-hour planned maintenance window. Zero overrun, zero re-work.

01 Challenge

Three aging PLC-5 systems controlling mill drive sequencing needed replacement before the upcoming crush season. Downtime window was fixed at 36 hours with no negotiation — any overrun would delay the season start.

02 Solution

We conducted a full logic audit and tag mapping in the weeks prior to shutdown, building the ControlLogix program in parallel against a simulation bench. All testing was completed off-site. On shutdown day, it was hardware swap and I/O verification only.

03 Outcome

36-hour planned outage. Zero overruns. System handed back to operators 2 hours inside the window with all interlocks verified and documented.

Background

Mackay Sugar’s Racecourse Mill had been running three PLC-5 systems controlling primary mill drive sequencing since the mid-2000s. Spare parts availability had become critical and one system had already suffered an unplanned failure mid-crush the previous season.

What we did

The migration covered approximately 1,400 I/O points across three control panels. We ran a full shadow program during the final weeks of the previous crush season — logging live signal states to validate our logic before we ever touched the hardware.

The physical cutover was a single-panel-at-a-time swap with immediate I/O verification at each stage, using a structured commissioning checklist signed off by the mill’s own electricians at each hold point.

Result

The mill started the following crush season with no PLC-related stoppages. The site now has a single programming environment across all drive controls, and the maintenance team can modify sequences without engaging an external contractor for every change.

Technologies used
Rockwell ControlLogix Studio 5000 PanelView Plus 7 RSLinx

"Beetle rewrote our entire crusher control logic during a 10-day shutdown. Clean code, proper documentation, no surprises on startup."

Electrical Superintendent Bowen Basin Coal Operations
Services involved

What we delivered

All services →

Similar project on your site?

Get in touch to discuss what's involved. We work across mining, sugar, manufacturing and utilities in Central Queensland.